March 2012
In February 2012 the commissioning of power plant Wanta 4 in Taiwan has started. First step in commissioning of electro mechanical equipment was to put in operation the main transformer (33.5 MVA). At the same time protection and SCADA systems were tested and put in permanent operation. Turboinstitut and partners supplied the power plant with turbine, turbine governor, generator, protection and SCADA systems.
|